Tag Archives: testing

The schedule of transformer oil maintenance oil type transformer maintenance

oil type transformer maintenance

The frequency of transformers maintenance depends on the importance, design features and durability of transformers. The first step towards a preventive maintenance program is testing. Testing helps us to determine when a treatment is necessary.

WHY DO WE NEED TO CHECK TRANSFORMER OIL?

Transformer oil is an insulator between the metal parts of the transformer and the wiring within the tank. Over time, the oil can be contaminated with moisture or create combustible gases. By sampling and testing that oil, we can plan repairing or replacing the transformer before a failure occurs.

Maintenance Schedule for Oil Filled Power Transformers

Maintenance or Test

Recommended Interval

 

Reference

Transformer physical inspection

 

Annually

Leakage of oil and reading of MOG (Magnetic Oil Gage) of tanks

Daily

In case of unsatisfactory oil level in the MOG, oil to be filled in transformer and also the transformer tank to be checked for oil leakage. If oil leakage is found take required action to plug the leakage. If silica gel becomes pinkish, it should be replaced.

 

Dielectric strength test (BDV) and moisture content (PPM).

 

Annually

A dielectric strength is a measure of the voltage which is conducted by the transformer oil. At times it is the presence of contaminants which conduct electricity faster than the oil which in turn lowers the dielectric breakdown voltage

Neutralization test

 

Annually

This test which is carried out to ascertain the level of acid which is present in the oil. When oxidation occurs in the transformer oil, it leads to build-up of acid.

Dissolved Gas Analysis Test (DGA)

Annually for 132 KV transformer, once in 2 years for the transformer below 132 KV transformer and in 2 years interval for the transformer above 132 KV transformer.

 

It helps to analyze the gases which are present in the transformer oil.

Bushings– check of oil level

 

Weekly

If it is required, the oil to be filled in the bushing up to correct level. Oil filling to be done under shutdown condition.

 

Bushings –visual inspection

 

Annually

Bushings – visual inspection and cleaning

 

5 years

Interfacial tension test

This is a test which is carried out to detect the presence of polar compounds such as paint, varnish and paper.

Tan & delta test

One in two years

Finally the presence of water too is measured as water can decrease the dielectric breakdown voltage of the transformer oil

Colour test

This test indicates aging, quality and the presence of contaminants in the transformer oil.

Transformer excitation current test

 

5 years

Insulating oil   – DGA, physical,

and chemical tests

 

Anually

Top oil and winding thermometer

Inspection

 

Anually

Oil level indicator operation

 

5 years

Sudden pressure relay

5 years

oil type transformer maintenance

oil type transformer maintenance

So, for getting high performance and long functional life of the transformer, it is desired to perform various maintenance activities. GlobeCores’s oil reclamation equipment will keep your transformer oil in the best condition, providing with oil degassing, water and solids removal as well as acids reducing. It’s a fantastic transformer life!

Regeneration of Oil

Oil Regeneration today has become a very interesting and important subject.  Oils can be regenerated in a number of ways by different equipment and to varying degrees of purification.

GlobeCore has developed and built oil regeneration equipment for many different applications that involve regeneration and purification.  The equipment varies widely in terms of number of applications and the degree of regeneration desired by the operator and include the following:

  • oil regeneration
  • heat and vacuum purification of oil,
  • purification of oil by adsorbents
  • drying of transformer windings,
  • dehydration of oil,
  • degassing of oil,
  • reactivation and preparation of sorbents, including full regeneration of MINERAL oils with color lightening.

The following is a brief list of GlobeCore’s equipment for oil regeneration, putificaton and other industrial applications.

  • Themovacuum oil purification units, mobile oil plants: СММ-0.6; СММ-0.7(Р); СММ-0.6; СММ-1.0; СММ-1.7; СММ-2.2; СММ-4.0; СММ-4.3 and some other models;
  • Comprehensive oil restoration units, including heating, nitrogenation, drying and filtration of insulation oils: CMM-3, CMM-4, CMM-5, CMM-5М, CMM-6, CMM 10-10, CMM 10-10В, CMM 10-10Л, CMM 10-10М, CMM-12B, CMM-12B1, CMM-12B2, CMM-12B3, CMM-14B У1, CMM-14B1, CMM-14B2, CMM-10-3, CMM-10-3Е, UDV-2М, PDV-Е and other range.
  • units for purification, drying and removal of solids from transformer and turbine oils – MCU-2-U1, MCU-4-U1, MCU-4С-U1,  MCU-4А,  MCU-4СА,  MCU-4C, MCU-4CF, MCU-4CS,  MCU-4CSA, MCU-А, MCU-С, MCU 4Р-N, MCU 4Р-NС, MCU 4Р-NA, MCU 4Р-NСА,  BC-N, MCU-7, FSM-2, FSMB-110М etc;
  • Sorbent regeneration systems– BR, PS-1, PS-1А,  PS-1Е, BRPS, MCU-4Р-BR, zeolite drying cabinet
  • Systems and vacuum sections for drying of solid insulation of power transformers – “Iney-4″, ” Iney-4М”, ” Iney-5″, ” Iney 5М”, ” Iney-6″, ” Iney-4.1″, ” Iney-4.1М”, ” Iney-4.2″, ” Iney-4.2М”, vacuum units BV-1 and BPR;
  • Units for drying of air to dew point below -50°С – “Sukhovey”, ” Sukhovey-4″, ” Sukhovey-5″, ” Sukhovey-4Е” with two independent heaters
  • transformer and transformer oil heating units: NTML, NTML-160М, NTML-80М, NTML-120М, NTML-200М, NTML-240М, NTML-150Е, for parameters of processed oil: solid content no more than 5 (10) ppm, filtration from 5 to 20 micron
  • oil filtration systems – FUM-P, FUM-А, customized drying and solid removal systems for mineral oils up to 50 m3/hour capacity, purity class from 7 toо 11, filtration ratios from 20 to 2000, filtration fineness 1, 3, 5, 10, 20 and 40 micron;

The full range of GlobeCore products is presented in the attached file, and can also be seen on the company’s website at www.globecore.com

The company has a global dealership network, and the products are supplied to more than 80 countries world wide.  Certified explosion protection option is available. Production certified in accordance with ISO 9001 – 2000.