August 16, 2017

СММ-2,2 plant was started up in Jizan

August 8, 2017 our company’s operation personnel performed commissioning and adjustment of the CMM-2.2 unit  in  Jizan (Saudi Arabia).

This equipment is multifunctional, since in addition to cleaning insulating oils from mechanical impurities, water and gases, it also heats electric equipment with hot oil and vacuum drys power transformers. The plant’s capacity in drying and filtration mode, is 2.2 m3 / h, and in  degassing mode –...


August 7, 2017

A seminar on purification and regeneration of industrial oils will be held in Oldenburg on 27 September

Dear customers and partners! GlobeCore GmbH invites you to attend a seminar on purification and regeneration of industrial oils, which will take place on September 27 in Oldenburg (Germany).

Seminar program:

11: 00-11: 45 – Discussion of the influence of oil aging processes on the efficiency and operation of power transformers;

11: 45 – 11:55 – Short break;

11:55 – 13:00 – Report on...


June 8, 2017

Zimbabwe. Annual presentations of GlobeCore equipment

June 8, this year a number of presentations on GlobeCore equipment was held in Bulawayo (Zimbabwe).

It was only last year in August that similar presentations were held in the capital of Zimbabwe- Harare. Then, not all the representatives from Zimbabwe electrical industry could be present at the presentations. This called for a new opportunity for more participants to attend.

Traditionally, GlobeCore presented its equipment for...


June 4, 2017

Equipment commissioning in Finland

May 31, our company technical team completed the works under the contract on production, delivery and commissioning of a CMM-4/7 unit in Finland (Helsinki).

This equipment is designed for businesses that repair and install high-voltage oil-filled equipment. The first transformer it services was a 400 MVA  transformer.

Operating modes of the unit

CMM-4/7 operates in three modes. Each  mode performs a certain set of functions:

“Degassing mode”...

May 31, 2017

CMM-4/7 and CMM-12R installed and commissioned in Botswana

21-31 of May, GlobeCore team conducted a commissioning of 2 units in Botswana.

Now in Gaborone are operating 2 oil regeneration units – CMM-4/7 and CMM-12R. CMM-4/7 solves the problems of degassing, drying and cleaning from mechanical impurities of insulating oils. This unit heats oil before refilling 1150 kV power transformers with it, It also vacuum dries and evacuates transformers. The processing rate in degassing...


May 16, 2017

Pakistan. CMM-4/7 successfully starts its work

May 13, 2017, another GlobeCore plant was successfully put into operation.

In Lahore (Pakistan), a CMM-4/7 unit serviced the power transformers through heating, drying, cleaning, degassing and nitriding of the insulating oil. This equipment can provide ISO 4406 cleanliness class – / 14/12 of industrial oil. It also achieves moisture content  by weight below  5 g / t, and the volumetric gas content 0.1%.

GlobeCore transformer...


May 8, 2017

GlobeCore held a presentation in Ecuador on May 3-4

May 3-4, in Quito (Ecuador) GlobeCore together with Tcontrol S.A. organized and held a seminar on modern technologies for cleaning and regeneration of mineral oils, fuels and other petroleum products.

The event was part of a series of presentations held by GlobeCore. in order to raise the awareness of managers and specialists in the energy, fuel, chemical and petrochemical industries. It was also aimed at finding new...


April 30, 2017

CMM-0,6 unit is ready for transformer maintenance in Saudi Arabia

April 23 – 27, GlobeCore technical team visited Jeddah (Saudi Arabia).

The purpose of this trip was commissioning of a CMM-0,6 oil purification unit. This equipment cleans insulating oil from mechanical impurities, water and gases.

The unit’s components are assembled in a closed container and mounted on a single-axle trailer. The container has flap doors on the sides, and a hinged door at the back....


April 14, 2017

CMM-4/7 started up in Estonia

April 10, 2017 GlobeCore specialists started up a CMM-4/7 unit in Tallinn (Estonia).

This equipment is used by business engaged in installation, repair and operation of power transformers for degassing and filtration of insulating oil. Also, the units can be used to heat oil-filled electrical appliances with hot oil, for vacuum dehydration and evacuation of transformers.

CMM-4/7 thermal vacuum processing obtains the following oil parameters:

moisture content...

February 20, 2017

Start up of equipment in Indonesia

February 15 this year GlobeCore equipment was started up in Gresik (Indonesia).

This time the CMM-0.6M oil purification plant was put into operation. This equipment is designed to clean insulating oils from water and mechanical impurities and can be used in installation, repairs and operation of power transformers.

The main difference of an CMM-0,6M plant from other equipment is its ability to process oil on...


February 12, 2017

GlobeCore at Gulf Industry Fair 2017

February 7 -9, 2017 Manama (Kingdom of Bahrain) hosted the Gulf International Industry Fair 2017.

It has been held since 2008. Over time, the Gulf Industry Fair 2017 has grown to a leading trade show in the Persian Gulf. According to the organizers, it has been visited by 30,000 people. The showcases of the Gulf Industry Fair 2017 were devoted to industrial products, equipment and machinery.

Read more


January 18, 2017

The CMM-10-10 unit was put into operation in Egypt

January 13, this year, GlobeCore employees completed commissioning of an UVM-10-10 unit in Asyut (Egypt).

This equipment is used during installation, repair and operation of power transformers. CMM-10-10 degasses and cleans insulating oils and vacuumizes transformers. After treatment the oil moisture content  is below 5 ppm, and gas content is 0.1%.

In addition to transformers in city substations, CMM units successfully service transformers on ships, offshore...


January 6, 2017

CMM-4/7 Units to Service Wind Farm Transformers in Virginia, US

GlobeCore is  a member of American Wind Energy Association (AWEA) and is a participant in many wind-power related projects.

In November one of American power generation companies contacted GlobeCore to rent two CMM-4/7 units, which were then shipped to Virginia to service wind farm transformers.

This type of equipment removes solves gas, solved and free water and particulate matter from transformer oil; it can also...


December 6, 2016

GlobeCore gains membership in the American Wind Energy Association (AWEA)

Our company always strives to keep abreast of latest trends in the power generation sector.

This approach allows us to follow the newest technologies to improve our equipment and solve practical problems. To be more involved with the wind power industry, GlobeCore joined the American Wind Energy Association (AWEA).

This decision stems from the work done by GlobeCore previously on transformers for marine environment which convert...


November 16, 2016

Guests from Ethiopia Visit the GlobeCore International Training Center in Oldenburg

On 14 November 2016 GlobeCore main office hosted visitors again.

This time, the visitors, interested in mineral oil and fuel treatment technologies, as well as efficient power transformer servicing, came from Ethiopia.

A GlobeCore specialist held a presentation for the guests, describing the capabilities of equipment designed for:

mineral oil filtration; mineral oil degassing; mineral oil regeneration; fuel purification and clarification; vacuum evaculation of power transformers; drying of power transformer solid insulation...

November 6, 2016

Canada. The CMM-4/7 unit for oil reclaiming successfully services transformers of wind turbines

Oil reclaiming extends power transformer service life fro 15 years.

GlobeCore is a member of the American Wind Energy Association (AWEA), and always tries to find solutions to the urgent problems in the industry.

Among the tasks are: increasing reliability and extending service life of wind turbine transformers. These transformers convert the voltage of turbine generators for power lines. They are positioned within the tower or...


October 10, 2016

WETEX International Exhibition in Dubai

October 4-6, Dubai (UAE) hosted the 18th WETEX 2016 international exhibition, which presented the latest water treatment technologies, energy technologies, and developments in environmental protection.

The event has been organized by Dubai Electricity and Water Authority (DEWA) since 1999. Now WETEX is one of the leading exhibitions which gathers representatives of the energy sector from around the world. This year more than 1500 participants (700 companies) from...


October 8, 2016

Oil Reclaiming and Oil Degassing Unit CMM-0.6 Launched in Italy

October 2016: GlobeCore technical support team commissions an oil reclaiming and oil degassing unit CMM-0.6 in Italy.

The oil reclaiming equipment will be operated in Carpenedolo, Brescia. The CMM-0.6 is a portable oil station that purifies electrical insulating oils, removing mechanical impurities, water and gas. It guarantees the desired oils parameters for oils with viscosity less than 70 cSt (at 50°C).

The equipment is in demand among facilities...


October 6, 2016

Oman. GlobeCore equipment presentation in Muscat

In October 2016, GlobeCore made a presentation of its equipment in Muscat (Oman).

The presentation was a part of the seminar organized by RAY International Group. The seminar was attributed to the issues of oil and gas industry in Oman.

It was attended by 50 delegates, among them the representatives of the oil and gas industry of Oman, companies engaged in transmission and distribution of energy,...


September 3, 2016

Successful Start up of CMM-12R unit for Oil Reclamation in Ecuador

August this year, our company visited the city of Quito (Ecuador), to start up a СММ-12R unit for Oil Reclamation

The startup was preceded by a test run, which demonstrated good results with reduced dielectric loss tangent of 0,7% at 90° C (initial value at 11%) and increase of breakdown voltage to 80 kV.

The main feature of the CMM-12R plant is the round...